INSTALLING INVERTERS | 
    
    
      
		  | 
    
    
      
		August 14, 2009 
		I decided not to wait for the remaining inverters and 
		start by installing the 12 (of 21) that I have so far.  These are 
		the brand new 
		Enphase M190 units 
		(now discontinued) that were in high demand and short 
		supply.  This installation is not going the way that I visualized 
		it -- I had pictured a barn raising with half a dozen friends taking a 
		day or so and we'd have the whole thing done.  Instead I'm doing it 
		piecemeal while I wait for the inverters to arrive. | 
    
    
      
		 I 
		 began at the bottom right and wired the cable end into the junction box 
		and then mounted the first inverter at the bottom right of the roof.  
		I had planned to run the AC circuit up 3, left 1, down 3, and on to the 
		left for 15 units.   
		 
		Each inverter's 240 Volt AC cable plugs into the next unit like 
		extension cords in series.  The maximum number of inverters per 
		group is limited by the 15 Amp circuit breaker, in this case my limit is 
		16 units and I'm installing 15 in the first group, and the remaining 6 
		in a second group.  Eventually I will add to the 2nd group as 
		finances allow.  But when I installed the second inverter above the 
		first I found that the AC cable built into the unit was not long 
		enough!   Whoa! 
		 
		So I called
		
		Enphase tech support and spoke with Eric.  I asked him 
		to look at my blog so he could see my layout and understand the issue.  
		He immediately offered to send me some 6ft. extension cables for free!  
		So I asked for 4 of them.  If I change the wiring sequence to start 
		at bottom right, go left 5, then up 1, then right 5, then up 1 then left 
		5 -- then I only need to go up twice per group of inverters.  The 
		second group will have 6 inverters to begin with and eventually 14 total 
		as I can afford to add to the system. 
		 
		The previous model M175 had AC cables with 
		male and female ends, the M190 has a male cable and a female connector 
		built into the unit.  I think the 2 cable design was better as it 
		allowed more flexibility in installation. 
		 
		Sept. 9, 2009.  An Enphase staffer told 
		me today that the cables have been extended 8" on all production units | 
    
    
      Here is a 
		system wiring diagram: 
		  
		 | 
    
    
      
		
		 I am mounting the inverters with an extra large washer, regular washer, 
		lock washer and nut over the right mounting slot.  The large washer is there to 
		cover the WEEB grounding washer to ensure it gets good even pressure on 
		it.  I used a 
		torque wrench to tighten the nuts per the
		Wiley Electronics 
		recommendations.   
		 
		Since I did not originally have a torque wrench, I looked for an 
		inexpensive one on the web and found one for about $15.00 at
		Harbor Freight Tools. 
		 
		 
		While they are known for cheap tools that are often not much good, this 
		tool has worked out fine on the job.  I have found many great 
		bargains at Harbor Freight. 
		 
		Update April 14, 2010 
		Enphase has released an app note clarifying how to use the WEEB grounding system 
		for their inverters. 
		Download 
		it here. | 
    
    
      
		
		
		
		
  
		September 3, 2009 
		
		  
		I finally got the last 9 inverters.  I had to scour the web to find 
		a supplier that had some in stock - they are selling out fast.  So 
		I went up on the roof and installed them today in preparation for 
		installing the remaining panels tomorrow. 
		 
		
		
		
		 | 
    
    
      
		
		
		
		
		  Here 
		are some images that show the WEEB grounding washer that I put beneath 
		the
		Enphase inverter bracket to ground it to the Genesys mounting 
		rail. 
		
		
		
		 | 
    
    
      
		
		
		
		
		  Here 
		I am torquing down the inverter mounts and plugging the inverter in to 
		the extension cable that goes down to the next row.  It's a 
		"plug-n-play" system! (Note that I had turned off the circuit 
		breaker before working on the roof!) 
		 
		Thanks to my wife,
		Rebekah 
		Younger for these photos | 
    
    
      
		
		
		
		
		 The 
		daisy chain wiring of the inverters terminates to a cable that comes 
		from a weatherproof junction box.  I used a larger than necessary 
		box to have plenty of room inside - could have used a smaller 4X4 box in 
		retrospect, but they are cheap.  Note the weatherproof wire 
		connection on the side of the box. | 
    
    
      
		
		
		
		Tomorrow, we'll install the solar panels to complete the 21 panel array. 
		 
		Here are 2 really good videos that detail the installation of a system 
		in New Jersey.  Very clear and detailed: 
		Part 1 New Jersey PV Solar Installation of a Enphase Energy Micro Inverter 
		system
		 
		Part 2 New Jersey 5.6 KW PV Solar Installation of a Enphase Micro Inverter
		system 
		 
		 
		 | 
    
    
      
		
		
		
				
				  | 
    
    
      | 
		
		
		
				 
					
		
		
		
				If you found the information presented on my web site to be helpful you 
		can send me a donation to show your appreciation for the many hours I 
		have invested in presenting my knowledge and experience.  This is 
		NOT tax deductible and will show as a consulting fee on your receipt. 
				
 |